February 13.
The scaffold has been removed from around the Digital Dome Theater, and the view from the corner is very impressive! Scaffold is being built next to the new stairway tower for the installation of the glass window panes.

February 13.
The insulation on the outside wall is being installed.

February 16.
The exterior panels are being attached.

February 16.
The window frames are being installed in the stairway tower.

February 22.
Plastic is installed in the tower for temporary weatherproofing.